作者 cookie1216 (cookie)標題 Re: [新聞] 英特爾俄亥俄州兩晶片廠 大幅延期 至少時間 Wed Mar 5 15:07:27 2025
新報告顯示,英特爾已為推遲的新奧爾巴尼晶片工廠花費數十億美元
Intel already spent billions on delayed New Albany chip factory, new report
reveals
https://reurl.cc/A6o5nK
英特爾在俄亥俄州的第一家工廠可能會被推遲數年,但該晶片製造商已經投入數十億美元
在利金縣新奧爾巴尼工廠建設工廠。
Intel's first Ohio factories may be delayed several years, but the chipmaker
has already spent billions of dollars to make its plants a reality at the New
Albany site in Licking County.
根據上週提交給俄亥俄州發展部的進度報告,截至 2024 年底,英特爾已花費 37 億美元
,並簽署了另外 32 億美元的合同,這意味著該公司已經承擔了約 69 億美元的責任。該
報告是英特爾與俄亥俄州達成的大型專案稅收抵免協議的一部分,每年提交一次。
As of the end of 2024, Intel spent $3.7 billion and has signed contracts for
another $3.2 billion in work meaning the company is already on the hook for
roughly $6.9 billion, according to a progress report filed with the Ohio
Department of Development last week. The report, which is part of the
Megaproject Tax Credit Agreement that Intel has with Ohio, is filed annually.
...
據報道,英特爾計劃在該地點開設兩座晶圓廠的第一座晶圓廠,建築工人已經澆築了
130,000 立方碼混凝土,並已開始安裝 600 根柱子和 320 塊板。工人們也已開始拼湊第
一家工廠屋頂的鋼桁架。舉例來說,13 萬立方碼相當於在一英畝的土地上澆築一塊近
27 英尺高的固體混凝土塊。
On the first of two fabs Intel intends to open on the site, construction
workers have already poured 130,000 cubic yards of concrete and have begun
installing 600 columns and 320 slabs, according to the report. Workers have
also begun piecing together the steel trusses of the roof for the first
factory. For context, 130,000 cubic yards would equate to pouring a nearly
27-foot solid concrete block over an acre.
根據該公司的報告,工人們已在第二座工廠澆築了約 50,000 立方碼的混凝土,並安裝了
兩台起重機來幫助建造第二座工廠。景觀美化也於 2024 年開始,該公司在整個場地種植
了 4,500 多棵樹和 1,400 多棵灌木。
On its second fab, workers have poured around 50,000 cubic yards of concrete
and two cranes have been installed to help build the second facility,
according to the company's report. Landscaping also began in 2024 with the
company planting more than 4,500 trees and 1,400 shrubs across the property.
...
英特爾與俄亥俄州發展部達成協議,向該公司提供 3 億美元的補助金,用於協助建造每
家工廠,前提是這些工廠必須在 2028 年底前完工。
An agreement between Intel and the Ohio Department of Development offered the
company $300 million in grants to help with the construction of each factory,
as long as they were completed by the end of 2028.
進度報告也首次透露,英特爾將把第一家半導體工廠的開幕時間延後至2030年或2031年。
The progress report for the first time also revealed that Intel delayed the
opening of its first semiconductor factory to 2030 or 2031.
英特爾第一家工廠原計劃於 2025 年開始運營,到正式投產時,將面臨至少五六年的延遲
。英特爾第二家工廠至少在2031年前不會完成,並預計自2032年開始營運。
By the time it opens, Intel's first factory will have faced at least five or
six years of delays, as it was originally scheduled to begin operating in
2025. Intel's second Ohio factory won't be completed until at least 2031 and
will begin running in 2032, according to the company.
心得:
Intel已經砸了至少37億美元在俄亥俄州的工廠建設上,
但這些工廠的建設進度被大幅延後至少5至6年,
可能會對Intel造成更沉重的財務負擔。
--
※ 發信站: 批踢踢實業坊(ptt.cc), 來自: 36.226.197.116 (臺灣)
※ 作者: cookie1216 2025-03-05 15:07:27
※ 文章代碼(AID): #1dn_WpKA (Stock)
※ 文章網址: https://www.ptt.cc/bbs/Stock/M.1741158451.A.50A.html
※ 同主題文章:
Re: [新聞] 英特爾俄亥俄州兩晶片廠 大幅延期 至少
03-05 15:07 cookie1216
推 almanch: 川: GG好像很有錢 呵呵1F 03/05 15:08
噓 pongp0416: 整版滿滿的INTC搞笑蛙就知道一堆邏輯錯誤的4F 03/05 15:11
推 Yahweh: 美:無所謂了 我們有ASMC5F 03/05 15:13
→ ilanese: 別蓋了!直接給台積電代工,省錢又好!8F 03/05 15:20
推 Swave: 新的乾兒子已經過戶入籍了,這沒出息的不用管他了11F 03/05 15:22
→ uv5566: 補助騙完 裝死擺爛惹12F 03/05 15:25
推 gino0717: 不需要了 有更好玩的要過去了15F 03/05 15:30
推 CLisOM: 還沒蓋好各位就知道有種多少樹,美化有必要那麼快完成?18F 03/05 15:53
推 uire: 美:我有更聰明更棒的兒子了 這個不成材的不要了XD20F 03/05 15:57
推 Qpera: 美:還好我兩個兒子有一個有出息21F 03/05 16:09
→ kiddsw: 後續的晶片法補足 剛被三浦砍了 可憐
補助23F 03/05 16:11
推 akanokuruma: 五年之後才建好的東西可能三星都已經超車超到太空MAGA派仿照川普的方式搶過來就好26F 03/05 16:17
→ boringuy: 樹都種了,不用等樹長大嗎?31F 03/05 18:31
推 dickey2: 前省下來給台積電就好了32F 03/05 18:45
→ raku: 現在廢掉晶片法那intel直接一記重拳 畢竟它拿最多補助且財務狀況不佳33F 03/05 23:12
--